April 2023 – July 2023
SHP Construction & Civil carried out the conversion of a storage room into a new tuckshop, the construction of a new covered area, and a new concrete pathway. The project consisted of demolition of the ceiling (including asbestos removal) and internal wall within the building, removal of existing vent blocks and supply and installation of new door and Crimsafe windows. New fit out works included new FC ceiling, joinery and an exhaust system, new electrical, mechanical and hydraulic components, a complete repaint and new flooring throughout. SHP supplied and installed stainless steel sinks and benches, appliances and various fixtures along with the reinstatement of others from the old tuckshop.